COMBATTING RECURRING FLOODING THROUGH ADVANCED WATERWAY MANAGEMENT
The Fairbank Silverthorn Storm Trunk Sewer System represents a transformative investment in stormwater infrastructure for the City of Toronto. Valued at approximately $400 million, this critical initiative is designed to combat chronic flooding while modernizing aging infrastructure originally constructed in the 1950s.
Spanning four city wards, Toronto St. Paul’s, Eglinton–Lawrence, Davenport, and York South, the project delivers a comprehensive waterway management solution. At its core is a three-kilometre-long, 4.5-metre diameter storm trunk sewer, supported by 17 kilometres of collector sewers and 320 inlet control devices, including maintenance holes, catch basins, headwalls, and interconnected piping.
Once complete, the system will significantly strengthen the area’s resilience to extreme weather events by:
Funded by the City of Toronto with support from the Government of Canada, this project represents a long-term commitment to sustainable water management and community protection.
THE CHALLENGE
The Fairbank Silverthorn community has experienced repeated flooding over the past decades, with major storm events in 2000, 2005, and 2008 exposing the limitations of the existing combined sewer system.
Addressing these recurring issues required more than capacity upgrades and demanded a resilient, forward-looking solution capable of managing increasing storm intensity within a dense urban environment. The project called for deep tunneling through complex ground conditions, installation of large-diameter infrastructure in soft soils, and execution within tight timelines while minimizing disruption to surrounding communities and maintaining strict safety standards.
THE SOLUTION
To support this large-scale waterway management initiative, DECAST supplied precision-engineered Precast Concrete Tunnel Liner (PCTL) segments designed for high-performance tunneling applications.
With a 4500 mm internal diameter and 5000 mm external diameter, each ring was composed from six pieces. The system was designed and engineered to deliver both structural integrity and long-term hydraulic efficiency.
Gasketed joints ensure watertight performance, preventing infiltration and exfiltration, which are critical for protecting surrounding soils and nearby waterways. Integrated features such as bolt pockets, alignment indicators, and grouting sockets enabled efficient installation and consistent assembly within the tunnel environment.
Manufactured in a controlled facility setting, each segment achieved exceptional dimensional accuracy, consistent concrete quality, and durability required for long-term stormwater conveyance.
Key Product Features
INSTALLATION & EXECUTION
Tunneling operations began on May 8, 2023, with the launch of a 270-tonne Earth Pressure Balance Machine (EPBM) from a 40-metre-deep shaft at Fairbank Memorial Park. The TBM is approximately 80 metres long when assembled, advancing through soft ground conditions while installing precast segments in real time.
A continuous, synchronized process of excavation, segment placement, ring assembly, bolting, and grouting ensured steady progress and high productivity. On October 2, 2024, the machine successfully broke through the extraction shaft, marking a major milestone in the project.
Installation Process
In total, 2,410 metres of tunneling were completed, with approximately 1,850 rings installed by EBC Bessac, specializing in large-scale tunneling and underground projects. Operations achieved an average production rate of 10.5 rings per day (approximately 13.6 metres), supported by continuous weekday operations.
MANUFACTURING EXCELLENCE
DECAST maintained a production rate that exceeded installation demand, ensuring a consistent and reliable supply of segments to the project site. With limited on-site storage, segments were strategically staged at our Stouffville facility and delivered in sequence to align with tunneling operations.
This delivery approach optimized the sites efficiency while reducing congestion and handling requirements. The use of PCTL’s has resulted in many benefits to the project, some of which are listed below.
Enhanced Safety
Environmental & Community Benefits
Quality & Performance
The Fairbank Silverthorn Storm Trunk Sewer System demonstrates DECAST’s ability to deliver engineered solutions that directly address recurring flood challenges while supporting sustainable waterway management.
Through advanced precast technology, coordinated logistics, and engineering expertise, DECAST has contributed to a resilient infrastructure system that protects communities, preserves local waterways, and supports the City of Toronto’s long-term stormwater management strategy.
Project Details
Location: City Of TorontoCopyright 2026 DECAST LTD. | Accessibility | All Rights Reserved | (800) 461-5632 Developed by MediaSuite Inc.
Registered in Canadian Patent and Trademark Office